Proceedings of the Nineteenth International Joint Conference on Artificial Intelligence. Pages 181-185.

© 2005 International Joint Conferences on Artificial Intelligence

Abstract

This paper describes a simple complete search for cumulative scheduling based on the detection and resolution of minimal critical sets (MCS). The heuristic for selecting MCSs relies on an estimation of the related reduction of the search space. An extension of the search procedure using selfadapting shaving is proposed. The approach was implemented on top of classical constraint propagation algorithms and tested on resource constrained project scheduling problems (RCPSP). We were able to close more than 15% of the previously open problems of the PSPLIB [Kolisch and Sprecher, 1996] and improve more than 31% of the best known lower bounds on those heavily studied problems. Other new results on open-shop and cumulative job-shop scheduling are reported.

  1. UB Optim. Instance UB Optim. gp06-03 1255 1255* gp09-02 1112 1110* gp06-07 1290 1290* gp09-03 1117 1115* gp06-09 1243 1243* gp09-06 1093 1093* gp06-10 1254 1254* gp09-07 1097 1090* gp07-01 1159 1159* gp09-08 1106 1105* gp07-02 1185 1185* gp09-09 1126 1123* gp07-04 1167 1167* gp09-10 1120 1110* gp07-06 1193 1193* gp10-01 1099 1093* gp07-08 1180 1180* gp10-02 1099 1097* gp07-09 1220 1220* gp10-03 1081 1081* gp08-02 1135 1135* gp10-04 1089 1077* gp08-04 1154 1153* gp10-05 1080 1071* gp08-06 1116 1115* gp10-06 1072 1071* gp08-07 1126 1126* gp10-07 1081 1079* gp08-08 1148 1148* gp10-08 1098 1093* gp08-10 1161 1161* gp10-09 1120 1112* gp09-01 1135 1129* gp10-10 1092 1092*
  2. [Baptiste and Demassey, 2004] P. Baptiste and S. Demassey. Tight LP bounds for resource constrained project schedul- ing. OR Spectrum, 26:251-262, 2004.
  3. [Blum, 2005] C. Blum. Beam-ACO -hybridizing ant colony optimization with beam search: an application to open- shop scheduling. Computers & Operations Research, 32(6):1565-1591, 2005.
  4. [Brucker and Knust, 2000] P. Brucker and S. Knust. A lin- ear programming and constraint propagation-based lower bound for the RCPSP. European Journal of Operational Research, 127:355-362, 2000.
  5. [Brucker et al., 1997] P. Brucker, J. Hurink, B. Jurisch, and B. Wöstmann. A branch & bound algorithm for the open- shop problem. Discrete Applied Mathematics, 76:43-59, 1997.
  6. [Demeulemeester and Herroelen, 2002] E. Demeulemeester and W. Herroelen. Project scheduling -A research hand- book. Kluwer Academic Publishers, 2002.
  7. [Garaix et al., 2005] T. Garaix, C. Artigues, and S. De- massey. Bornes basées sur les ensembles interdits pour le problème d'ordonnancement de projet à moyens limités. In ROADEF'2005, 2005.
  8. [Guéret and Prins, 1999] C. Guéret and C. Prins. A new lower bound for the open-shop problem. Annals of Op- erations Research, 92:165-183, 1999.
  9. [Hartmann and Kolisch, 2005] S. Hartmann and R. Kolisch. Experimental evaluation of state-of-the-art heuristics for the resource-constrained project scheduling problem: An update. European Journal of Operational Research, 2005.
  10. [ILOG, 2005] ILOG. ILOG SCHEDULER 6.1 Reference Manual, 2005. http://www.ilog.com/. Link
  11. [Kolisch and Sprecher, 1996] R. Kolisch and A. Sprecher. PSPLIB -A project scheduling problem library. European Journal of Operational Research, 96:205-216, 1996.
  12. [Laborie and Ghallab, 1995] P. Laborie and M. Ghallab. Planning with Sharable Resource Constraints. In IJCAI- 95, pages 1643-1649, 1995. IJCAI
  13. [Laborie, 2003] P. Laborie. Algorithms for propagation re- source constraints in AI planning and scheduling: Exist- ing approaches and new results. Artificial Intelligence, 143:151-188, 2003.
  14. [Nuijten, 1996] W. Nuijten. A computational study of constraint satisfaction for multiple capacitated job shop scheduling. European Journal of Operational Research, 90(2):269-284, 1996.
  15. [Torres and Lopez, 2000] P. Torres and P. Lopez. Overview and possible extensions of shaving techniques for Job- Shop problems. In CP-AI-OR'2000, pages 181-186, 2000.
  16. [Vilain and Kautz, 1986] M. Vilain and H. Kautz. Constraint propagation algorithms for temporal reasoning. In Fifth National Conference on Artificial Intelligence, pages 377- 382, 1986.

References were extracted automatically from the PDF and may contain errors.

Welcome Future Conferences AI Journal Division IJCAI Proceedings About IJCAI IJCAI Awards